On December 1, 2017, the pavements of line 2 from Andimeshk station kilometer 818+674 to Sabz Aab station kilometer 582+690 with an approximate length of 16 kilometers, and on February 2, 2017, from Sabz Aab station kilometer 582+690 to Shoosh station kilometer 519+705 with the approximate length of 15 kilometers reached the operational stage and those areas have been delivered to Zagros Railway Administration.
Shoosh to Ahoodasht station with a length of 47 kilometers is operational and includes the undermentioned blocks:
- Shoosh-Haft Tape with a length of 16 kilometers
- Haft Tape-Mian Aab with a length of 16 kilometers
- Mian Aab-Ahoodasht with a length of 15 kilometers